Work Breakdown Structure

last modified on 2014-10-15

Estimates Explanation

Hours listed below do not correspond to calendar time.  They are staff hours (also known as man hours).

Additionally, this Work Breakdown Structure (WBS) utilizes the 3-point estimation method from Project Evaluation and Review Techniques (PERT) and project buffer from Critical Chain Project Management (CCPM).  The estimates listed next to each task are the 50% confidence estimates, which means that there is a 50% probability that the corresponding task will be completed within the estimated time.  Time from the buffer will be used for tasks that go over the estimate and time will be added back to the project on tasks that complete in less time than the estimate.

 

Project WBS

  • Discovery - 13.5 hours
    • Research options - 3 hours
    • Gather Requirements - 9.5 hours
    • Gather signatures - 1 hour
  • Design - 12.5 hours
    • Create technical specifications - 5 hours
    • Create Mock-ups - 5.5 hours
    • Get design approval - 2 hours
  • Development - 119.5 hours
    • Register as developer with 3rd parties - 3 hours
    • Develop product - 83.5 hours
    • Theme product - 30 hours
    • Alpha test - 1.5 hours
    • Code review - 1.5 hours
  • Deployment - 20.5 hours
    • Package application - 2 hours
    • Deploy to staging environment - 1.5 hours
    • Update and test QA checklist - 13.5 hours
    • Inform sponsor to start UAT and answer questions - 2 hours
    • Deploy application to production environment - 1.5 hours
  • Project schedule buffer - 64 hours

Total Project Time: 230 hours